MECHANICAL – OVERHEAD CASE CONVEYOR
PROJECT NAME
Overhead Case Conveyor Case Study: This project occurred in November of 2025.
Project Scope: The project scope included removal and disposal of 900 lineal feet of floor level and overhead case conveyor from the packer discharge to the palletizer infeed.
- Installation of the new conveying system was done by the new equipment OEM.
- Full demo and clean up was completed in (1) 24-hour period.