ENGINEERING – PALLETIZER REPLACEMENT
PROJECT NAME
Palletizer Replacement Project Case Study:
This project installation occurred in (3) 1-week phases from August 2025 – October 2025.
The overall scope:
- Replace (2) existing palletizers with (2) new 4-zone Ttek palletizers
- Relocate and (2) other existing palletizers to align the empty pallet infeed
- Replace the existing empty pallet feed system with a new automated T-Car system
- Replace 1200sqft of operator platform for the palletizer bank
- Replace/relocate full pallet and finished goods conveyance outfeed of all (4) palletizers.
- Replace case conveyor infeed of (3) palletizers
- OMS was engaged for a turn key project including full project management, engineering design, installation, and commissioning.